Basslink has revealed that its dispute with the state of Tasmania will be referred to arbitration after the two were unsuccessful in resolving it during "without prejudice" meetings.

"Unfortunately, the dispute was not resolved, and has led to Basslink being notified by the state today that the dispute is referred to arbitration. Basslink intends to vigorously defend itself in the arbitration and continues to reserve all its rights in this matter," it said on Friday.

"Basslink maintains its position that there is no proper basis for these claims."

The Tasmanian government had last month said it is seeking AU$122 million in compensatory damages[1] from Basslink due to a months-long outage of the wholesale telecommunications and energy subsea cable.

Basslink has continually refuted claims by the state government[2] that it breached the Basslink Operations Agreement (BOA) contract it has as the operator of the submarine cable.

"As part of the commissioning of the Basslink Interconnector in 2006, the Basslink Interconnector was rigorously tested to ensure the design and construction requirements were satisfied," the company previously said.

"Given that the Basslink Interconnector was completed and commissioned more than a decade ago, Basslink is extremely surprised at these very belated allegations by the state and strenuously denies that any warranties under the BOA were breached."

According to Basslink, an independent inspector had signed off the design, construction, and commissioning requirements.

"The state, through Hydro Tasmania, was very closely involved in the design, construction, and commissioning process. This involvement included attending various meetings with both Basslink and the manufacturers," the company argued.

"Basslink maintains the cable failure was a force majeure event."

The Tasmanian government's threats of legal action against Basslink[3] followed reports from two global experts

Read more from our friends at ZDNet